PEGASUS 70

This project was the first of five successful projects working with well known international yachtsman Philippe Kahn.

This project was also the first opportunity that David Lake Yachting Projects had to work in close association with Alan Andrews Yacht Design. The Pegasus 70 project was executed in two distinct phases.

pegasius 70 aerial sailing

Additional Pegasus 70 Photos

David Lake Yachting Projects managed both phases of this project at Dencho Marine on a daily basis with close liaison with Alan Andrews Yacht Design.

Project Management services provided included:

  • Overall planning
  • Scheduling
  • Budget preparation
  • Invoice review
  • Specification review
  • On site project supervision
  • Hiring of sub contractors
  • Sailing trials

Phase One

  • The primary focus of phase one was to lengthen- two feet- and re ballast in nine weeks.
  • Complete exterior painting to include new graphics.
  • Modify navigation station.
  • Electronic upgrade.
  • Fit new cabin sole.
  • Modify internal structure.
  • Fit new foil, bulb and kelp cutter.
  • Build and fit new spars.

Phase Two

  • The focus of this project was to complete a deck and interior refit in seven weeks.
  • Refitting of new deck hardware to a revised deck plan.
  • Adding stern scoop and new cockpit.
  • Removing all unnecessary interior equipment to reduce weight
  • Rebuilding of structural components.
  • Repainting the interior and deck.
  • Installing a new steering system.
  • Complete electronics review and upgrade.
  • Revised crew stowage areas.